Video HLI Ecohub Nam Ha Construction Progress Update - April 2025

15/04/2025

Video HLI Ecohub Nam Ha Construction Progress Update - April 2025
Entering the beginning of Q2/2025, HLI EcoHub Nam Ha is accelerating construction on several key items, reaffirming our commitment to quality and the scheduled handover in Q3/2025.

 Check out the latest images with Hoa Long Invest:

🏭 FACTORY ZONE:

- Installation of steel structure and concrete pouring for the mezzanine deck floor

- Installation of roof sheeting, boundary walls, and wall plastering

 

 

INFRASTRUCTURE:

- Stormwater drainage line installation: 65% complete

- Wastewater drainage line installation: Ongoing

AUXILIARY ZONE:

- Construction of underground fire protection water tank

- Installation of MEP system and ELV system

SPECIAL OFFER – EXCLUSIVELY AT HLI ECOHUB NAM HA:
 - Free fit-out up to 6 months 
 - Valid until June 30, 2025

📩 BOOK NOW to seize the investment opportunity in a green – flexible – cost-effective factory complex in Binh Thuan!

Du-an-nha-xuong-xay-san-hli-ecohub-nam-ha-04-1


Du-an-nha-xuong-xay-san-hli-ecohub-nam-ha-04-2
 

Du-an-nha-xuong-xay-san-hli-ecohub-nam-ha-04-4


Du-an-nha-xuong-xay-san-hli-ecohub-nam-ha-04-3
 

Du-an-nha-xuong-xay-san-hli-ecohub-nam-ha-04-5


Du-an-nha-xuong-xay-san-hli-ecohub-nam-ha-04-6
 

Du-an-nha-xuong-xay-san-hli-ecohub-nam-ha-04-8


Du-an-nha-xuong-xay-san-hli-ecohub-nam-ha-04-7
 

Du-an-nha-xuong-xay-san-hli-ecohub-nam-ha-04-9


HLI ECOHUB NAM HA READY-BUILT FACTORY  

  • Location: Dong Ha Commune, Duc Linh District, Binh Thuan Province
  • Hotline: 0964 582 346
  • Email: contact@hoalonginvest.com
  • Address: 19 Tran Quy Kien, Binh Trung Tay Ward, Thu Duc City, HCMC

Other news

Features

Hòa Long Invest & STX Việt Nam: Dấu Ấn Hợp Tác Chiến Lược Tại HLI EcoHub Nam Hà

Trong khuôn khổ Lễ Khánh thành Giai đoạn I và Khởi công Giai đoạn II Dự án HLI EcoHub Nam Hà, Công ty Cổ phần Đầu tư – Xây dựng Hòa Long (Hòa Long Invest) và Công ty TNHH STX Việt Nam đã chính thức ký kết hợp đồng thuê nhà xưởng sản xuất – kinh doanh tại dự án.

Features

Groundbreaking Of A Vnd 1,750 Billion Green Industrial Project: HLI Ecohub Nam Ha Ready-Built Factory – Phase II

On December 19, 2025, in Tra Tan Commune, Lam Dong Province, Hoa Long Invest solemnly held the Groundbreaking Ceremony for Phase II and the Inauguration of Phase I of the HLI EcoHub Nam Ha Ready-Built Factory Project.

Features

HLI ECOHUB NAM HÀ ĐƯỢC CHỌN LÀ MỘT TRONG BỐN DỰ ÁN TRỌNG ĐIỂM CỦA LÂM ĐỒNG, THAM GIA LỄ KHỞI CÔNG – KHÁNH THÀNH CHÀO MỪNG ĐẠI HỘI ĐẢNG LẦN THỨ XIV

Ngày 19/12/2025, tỉnh Lâm Đồng sẽ đồng loạt Khởi công và Khánh thành bốn dự án trọng điểm – một sự kiện có ý nghĩa lớn trong chuỗi hoạt động chào mừng Đại hội đại biểu toàn quốc lần thứ XIV của Đảng. Đây được xem là bước chuyển mình mạnh mẽ của địa phương trong nỗ lực thu hút vốn FDI chất lượng cao và định hướng phát triển kinh tế theo hướng bền vững.

Features

READY FOR A NEW MILESTONE: THE GROUNDBREAKING CEREMONY FOR PHASE II &THE GRAND INAUGURATION OF PHASE I – HLI ECOHUB NAM HA PROJECT

On December 19, 2025, HLI EcoHub Nam Ha will officially host the Groundbreaking Ceremony for Phase II and the Grand Inauguration of Phase I—a significant milestone in the development of a sustainable and green-oriented industrial ecosystem in Lam Dong Province.